UNIFIED LEYTE GEOTHERMAL POWER PLANT COMPLEX

Name of Plant: Unified Leyte Geothermal Power Plant Complex
Location: Tongonan, Leyte
IPP Operator: Energy Development Corporation
Type of Contract: Build-Own-Operate (BOO) – Power Purchase Agreement (PPA)
End of Cooperation Period:
Leyte-Cebu: 25 July 2021
Leyte-Luzon: 25 July 2022
Type of Plant: Geothermal Power Plant
Type of Fuel: Steam/Geothermal
Installed Capacity: 589 MW
Guaranteed Energy: 3,933 GWh (min) to 4370 GWh (max) per year
Note: 200 MW Strips of Energy was assigned to the IPPAs in December 2014.
GENERAL SANTOS BUNKER C - FIRED THERMAL POWER PLANT

Name of Plant: General Santos Bunker C-Fired Thermal Power Plant
Location: Alabel, Sarangani
IPP Operator: Southern Philippines Power Corporation (SPPC)
Type of Contract: Build-Operate-Own (BOO) - Energy Conversion Agreement (ECA)
End of Cooperation Period: 24 April 2016
Type of Plant: Diesel Power Plant
Type of Fuel: Bunker C/Diesel
Contracted Capacity: 50 MW
MINDANAO COAL-FIRED POWER PLANT

Name of Plant: Mindanao Coal-Fired Power Plant
Location: Villanueva, Misamis Oriental
IPP Operator: STEAG State Power Inc.
Type of Contract: Built-Operate-Transfer (BOT)-Power Purchase Agreement (PPA)
End of Cooperation Period: 15 November 2031
Type of Plant: Coal Plant
Type of Fuel: Coal
Contracted Capacity: 200 MW
CALIRAYA-BOTOCAN-KALAYAAN HYDROELECTRIC POWER PLANT

Name of Plant: Caliraya-Botocan-Kalayaan Hydroelectric Power Plant
Location: Lumban, Majayjay, and Kalayaan, Laguna
IPP Operator: CBK Power Company Ltd.
Type of Contract: Build-Rehabilitate-Operate-Transfer (BROT) – Power Purchase Agreement (PPA)
End of Cooperation Period: 07 February 2026
Type of Plant: Hydroelectric Power Plant
Type of Fuel: Hydro
Contracted Capacity: 728 MW