PLANT PROFILE
457.73 MW Makban Geothermal Power Plant Complex

Location: Southern Luzon Bay & Calauan, Laguna                 and Sto. Tomas, Batangas

Approximately 70 km east of Metro Manila

Fuel Type:Geothermal Steam supplied by Unocal                  Philippines, Inc. (UPI)

Status: Rehabilitated

Unit Installed Capacity Commissioning Date
Plant A 2 units x 63 MW = 126 MW

1979

Plant B 2 units x 63 MW = 126 MW 1980
Plant C 2 units x 55 MW = 110 MW 1984
Plant D 2 units x 20 MW = 40 MW

1995

Plant E 2 units x 20 MW = 40 MW 1996
Binary Plant (modular units) 5 units x 3 MW = 15 MW
1 unit x 0.73 MW = 0.73 MW
1994
1994
     
Technical Specifications:
Turbine:
 
  Plants A-E Mitsubishi Heavy Industries, Japan
 
Binary Plant
ORMAT
Generator:    
  Plants A-E Mitsubishi Heavy Industries, Japan
  Binary Plant ORMAT